Planting generally takes place between June and August. Eucalypt seedlings are planted using a Pottiputki planting tool. A single person can comfortably plant up to 3000 trees a day using a Pottiputki. Pine seedlings can be planted with a tractor-mounted planting machine or by hand. Growers should ensure they order seedlings from reputable nurseries.
It is important upon receiving your seedlings that you:
In summary, table 2 is an example of typical on-ground works, recommended timings and indicative costs per hectare for a plantation established in 2005.
| Works | Recommended Timing | |
|---|---|---|
|
Spring spray to kill, prevent/ reduce seed set of problem weeds (eg. bracken, sorrel, phalaris and flatweed) |
September/ October 2004 | - |
| Order seedlings | December/ January 2004 |
$400/1000 for eucalypts $345/1600 for pines |
| Cultivation - Ripping / Mounding | March 2005 | $180-$250/ha |
| Fencing (if required for browsing control) | March 2005 | $2000-$3000/km (to keep out wallabies and possums) |
| Pre-plant weed control (at least 6 weeks prior to planting) | May 2005 | $25/ha (labour) and herbicide costs |
| Planting - seedlings (at least 6 weeks after spraying) | June/July 2005 |
$130/ha for eucalypts $200/ha for pines |
| Post plant weed control first year 'remedial' (if required) | September/October 2005 | - |
| Second year weed control | May 2006 | $45/ha (labour) and herbicide costs |
| Fertilising (if required based on foliar analyses) | - | $80/ha (labour) and fertiliser costs |
| TOTAL (excluding fencing costs) | - | Approx $850 - $1000/ha |